Facility for Refugees in Turkey

 

SUMMARY OF:

Commission Decision C(2015) 9500 — Refugee Facility for Turkey

Commission Decision C(2016) 855 — amending Decision C(2015) 9500

Commission Decision C(2017) 2293 — Facility for Refugees for Turkey

Commission Decision C(2018) 1500 amending Decision C(2015) 9500 — contribution to the Facility for Refugees in Turkey

WHAT IS THE AIM OF THE DECISIONS?

  • Decision C(2015) 9500 aims to help Turkey deal with the inflow of refugees* resulting from the Syrian crisis, Turkey being a major first reception and transit country for migrants due to its geographical position. It sets up the Refugee Facility for Turkey (the ‘Facility’).
  • Decision C(2016) 855 amends Decision C(2015) 9500, clarifying the scope of actions, other than humanitarian assistance, the Facility will coordinate, as well as the role and operation of the Facility’s steering committee. It also modifies the split of allocations between the general budget of the EU and EU countries’ contributions.
  • Decision C(2017) 2293 amends Decision C(2015) 9500, clarifying that no interest is due for the late payment by an EU country of a contribution to the Facility.
  • Decision C(2018) 1500 amends Decision C(2015) 9500, granting an additional tranche of €3 billion for the Facility as stated in the EU-Turkey Statement of March 2016.

KEY POINTS OF THE 2015 DECISION

  • To assist Turkey in addressing the immediate humanitarian and development needs of the refugees, their host communities, national and local authorities a coordination mechanism is established: the Refugee Facility.
  • The Facility’s objective is to ensure that actions financed with financial contributions from the EU countries and the general budget of the EU are properly coordinated and streamlined.
  • The budget set for the Facility is €3 billion, comprising:
    • €0.5 billion from the EU budget; and
    • €2.5 billion in the form of contributions from the EU countries as external assigned revenue*, according to a breakdown set in the annex to the decision and based on the Gross National Income Key*.
  • The European Commission coordinates the Facility by setting priorities for the allocation of resources.
  • The Facility is led by a steering committee providing strategic guidance. This committee is composed of two Commission representatives and a representative from each EU country, as well as a representative of Turkey in an advisory capacity. The Commission chairs the committee and provides its secretariat.
  • The Commission is responsible for managing the Facility in compliance with the relevant EU legislation providing the legal basis for the respective actions and their implementation.

Amendments in 2016, 2017 and 2018

The decision was amended in 2016 by Decision C/2016/855:

  • The mechanism is renamed ‘Facility for Refugees in Turkey’.
  • It clarifies the types of measures to refugees that may be coordinated through the Facility. These include
    • humanitarian assistance;
    • education;
    • health;
    • socio-economic support;
    • migration management; and
    • municipal infrastructure.
  • The role and functioning of the steering committee is further detailed.
  • The Facility’s budget is revised as follows:
    • within the €3 billion budget, the share of the contribution from the general EU budget is increased to one third;
    • the share of the EU countries is reduced to €2 billion;
    • the breakdown of contributions between EU countries is based on the Gross National Income Key used for the 2015 budget (the annex has been deleted).

Because the decision still referred to Regulation (EU, Euratom) No 966/2012 on the financial rules applicable to the EU’s general budget, the decision was amended a second time in 2017 by Decision C(2017) 2293. It clarifies that:

  • EU countries’ contributions to the Facility are voluntary and, unlike in the case of the EU’s own resources (i.e. the EU budget’s main sources of revenue), do not correspond to a pre-existing obligation;
  • as an exception to the financial rules that apply to the EU’s general budget, no interest is due for the late payment by an EU country of a contribution to the Facility.

In 2018, the decision was amended again further to the undertaking by the EU in the 2016 EU-Turkey Statement to mobilise a further €3 billion under the Facility for Refugees, under certain conditions, because the initially allocated €3 billion were about to be used to the full. This second tranche — to ensure the continuity of the Facility’s work for the 2018–2019 period — would follow the same pattern of distribution (i.e. €2 billion from EU countries and €1 billion from the EU budget).

Reports

The Commission publishes annual reports on the Facility’s operations.

FROM WHEN DO THE DECISIONS APPLY?

  • Decision C(2015) 9500 has applied since 1 January 2016.
  • Decision C(2016 855 has applied since 7 March 2016.
  • Decision C(2017) 2293 has applied retroactively from 10 February 2016, in order to cover the contributions already made by EU countries.
  • Decision C(2018) 1500 has applied since 14 March 2018.

BACKGROUND

For more information, see:

KEY TERMS

Refugees: people forced to leave their country and seek refuge from conflicts, violence, human rights violations, persecutions and natural disasters.
External assigned revenue: funds that are not part of the EU budget and come separately from the parties participating in the Facility.
Gross National Income Key: a matrix containing countries’ Gross National Income data which is used to determine fair burden-sharing.

MAIN DOCUMENTS

Commission Decision C(2018)1500 of 14 March 2018 on the Facility for Refugees in Turkey amending Commission Decision C(2015) 9500 as regards the contribution to the Facility for Refugees in Turkey (OJ C 106, 21.3.2018, pp. 4-6)

Communication from the Commission to the European Parliament and the Council — Second Annual Report on the Facility for Refugees in Turkey (COM(2018) 91 final, 14.3.2018)

Commission Decision C(2017) 2293 of 18 April 2017 on the Facility for Refugees in Turkey amending Commission Decision C(2015) 9500 of 24 November 2015 (OJ C 122, 19.4.2017, pp. 4-5)

Communication from the Commission to the European Parliament and the Council — First Annual Report on the Facility for Refugees in Turkey (COM(2017) 130 final, 2.3.2017)

Commission Decision C(2016) 855 of 10 February 2016 on the Facility for Refugees in Turkey, amending Commission Decision C(2015) 9500 of 24 November 2015 (OJ C 60, 16.2.2016, pp. 3-6)

Commission Decision C(2015) 9500 of 24 November 2015 on the coordination of the actions of the Union and of the Member States through a coordination mechanism — the Refugee Facility for Turkey (OJ C 407, 8.12.2015, pp. 8-13)

Successive amendments to Decision C(2015) 9500 have been incorporated into the original text. This consolidated version is of documentary value only.

RELATED DOCUMENTS

Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council of 25 October 2012 on the financial rules applicable to the general budget of the Union and repealing Council Regulation (EC, Euratom) No 1605/2002 (OJ L 298, 26.10.2012, pp. 1-96)

See consolidated version.

last update 13.10.2017